Hotel/Marina: 1 284 345 2657 Boatyard: 1 284 345 2658

Defiance Building Update

Construction of Defiance has been running smoothly and on schedule. The roofs have been mounted on the two-story condos and they are working on mounting the three-story condos this week. The galvanized roofing is due to arrive on island next week at which point they can begin installing. The interior walls have been plastered as well as much of the exterior.  Windows have also begun to be installed.

Click here for more photos

Leave a Comment

You must be logged in to post a comment.