Construction of Defiance has been running smoothly and on schedule. The roofs have been mounted on the two-story condos and they are working on mounting the three-story condos this week. The galvanized roofing is due to arrive on island next week at which point they can begin installing. The interior walls have been plastered as well as much of the exterior.  Windows have also begun to be installed.