We are happy with the recent progress of Defiance Block of Nanny Cay Village. The construction crew has been very busy. Since the last update, they have cast the slab grade beams, then striped all the formwork and have been back-filling to prepare for the steel work on the slab.

Last week they finished all the steel work on the slab and were able to cast the foundation on Friday March 13th. Over the weekend the crew have been working hard by putting up formwork and delivering blocks and building materials. At the beginning of the week they started to put up the block for the first floor walls. We are hoping to have the majority of the first floor block work up by the end of the week.

 

Visit the Defiance Gallery to see more photos of the construction progress.