Autumn updates on progress and improvements at Nanny Cay including marina, boatyard, hotel, eating and drinking, and general infrastructure.

Read More

Inner marina to be fully operational by December; Major infrastructural improvements coming this year including increased water production and storage; Boatyard getting new 60-tonne trailer; Owners committed to improving and hardening Nanny Cay to maintain its status as the Caribbean’s premier resort marina and boatyard.

Read More

The damage caused to the inner marina by Hurricane Irma on September 6th, has resulted in the need to completely replace the docks. This damage reduced our overall dockage capacity by 75%.

The current goal is to have the inner marina fully operational by November, with phased roll out of docks and services between now and then.

Read More

Piling for the new slips in the outer marina has been completed. Work continues on adding the pile caps and cabling and pedestals for shore power.

Read More

The year ended on a high note, as we opened the new outer marina after 17 months of construction. At a ceremony held at the entrance to the new outer marina on December 12, Premier and Minister of Finance, Dr. the Honourable D. Orlando Smith, OBE, declared the marina officially open.

Read More

A ceremony held at the entrance to the new outer marina last night (Monday, December 12), heralded its opening at Nanny Cay.

With speeches by Premier and Minister of Finance, Dr. the Honourable D. Orlando Smith, OBE, the Honourable Julian Fraser, and Miles Sutherland Pilch, general manager of Nanny Cay, the ceremony also included sailing demonstrations by the Royal BVI Yacht Club’s Youth Sailing programme and a kitesurfing flypast.

Read More

The unloading of the first 9 of 12 containers on the new peninsula at Nanny Cay heralded the arrival of the new docks for phase one of the new outer marina.

Two specialists from the docks’ manufacturers, Walcon Marine, arrived yesterday to start the Meccano-esque assembly of the pontoons. They are working with some of the Nanny Cay Projects team and Husky Salvage & Towing.

Read More

In July last year, construction started on a new outer marina at Nanny Cay. Here’s the progress date: The revetment is 90% complete, while dredging and construction of the 6.5-acre peninsula – which is a combination of dredged material and land we have literally moved from one side to the other – is 75% complete. Sheet piling to form the inner wall of the marina has started, and construction of the main access bridge is underway.

Read More

Another busy year for Nanny Cay. If you missed the news through the year, here are the highlights… January Rite Way kicked off the year by opening a new provisioning store, open 7 days a week from 7:00am – 7:00pm, is fully stocked with a wide range of groceries, chilled and frozen foods, fresh meat,…

Read More

On Thursday July 9, construction started on the Nanny Cay marina expansion project. The new Outer Marina will have 120 slips suitable for yachts from 30-75 feet with T-heads and a bulkhead capable of berthing megayachts up to 160′ in length.

Read More